title: "moneromooo: three months from November 2019"
|
|
author: moneromooo
|
|
date: 23 October 2019
|
|
amount: 395
|
|
milestones:
|
|
- name: first month
|
|
funds: 33.33% (131 XMR)
|
|
done: 1 December 2019
|
|
status: finished
|
|
- name: second month
|
|
funds: 33.33% (131 XMR)
|
|
done: 1 April 2020
|
|
status: finished
|
|
- name: third month
|
|
funds: 33.34% (133 XMR)
|
|
done: 27 June 2020
|
|
status: finished
|
|
payouts:
|
|
- date: 14 April 2020
|
|
amount: 262
|
|
- date: 28 September 2020
|
|
amount: 133
|
|
---
|
|
Hi,
|
|
|
|
I've been delaying this CCS because I'm going to have unknown time to work on Monero for the foreseeable future,
|
|
so I wasn't sure what to do. I've decided that the best is to continue as if normal, but the "months" may end up
|
|
taking more than a month, depending on how much time I spend on Monero. I cannot predict in advance how much of
|
|
my time will be spent on it. It may well be that I'll end up with full time on Monero, but there's no guarantee
|
|
of this at all. So, with this caveat clear to all, I apply for funding for the next three months' worth of work,
|
|
to cover November to January at least, and probably ending somewhat later than that. I'll still post monthly
|
|
updates along with how much time I put for that month.
|
|
|
|
Here's the link to my previous three months: https://repo.getmonero.org/monero-project/ccs-proposals/merge_requests/75
|
|
|
|
I have no particular things I'm planning to be working on as a definite, though I hope that CLSAG will be one of
|
|
them, if the audits get done. Dandelion was picked up by vtnerd. The new pay for service system could need some
|
|
more work. Otherwise it'll be whatever pops up at the time.
|
|
|
|
As usual, the target rate is $30 + 0.2 monero per hour, so with Monero currently at $53.63, we get 395 monero.
|
|
|
|
Thanks
|
|
|